Analisi Idraulica
0 violazioni piez ✓
3.74 MW idro TR7
7 tratte — disconnessione ai torrini
Q: 4.80 → TR1: -0.4 → TR3: -0.2 → TR6: -0.2 → Fine: 4.00 m³/s
DN2500 (TR1-TR3, 79.0km) v=0.90-0.98 m/s, J=0.19-0.22 m/km
DN2200 (TR4-TR7, 97.9km) v=1.05-1.10 m/s, J=0.30-0.33 m/km
Pelo libero torrini adattivo (margine arrivo ≥ 5m)
Carico residuo TR7: 112.0m → 3.74 MW (16,361 MWh/a)
Acciaio rivestito PE, ε=0.1mm (Darcy-Weisbach)
OPEX netto €5.64M/a
Costi €9.24M/a: Personale €3.5M, Manutenz. €2.24M, Royalty Todisco €2M, Energia €0.2M, Assicuraz. €1.3M
Ricavi €3.6M/a: Idroelettrico €2.8M, PV+Fibra €0.4M, Risparmi €0.4M
Todisco
10-15% SPV €60-90M | 20-30 GWh/a -10% | Royalty €3M/2M/1M decade | Tot €135-170M